Snowy weather in February impacts construction schedule for new Blakely school

Winter weather — including last month’s snowstorm that closed schools for days — has set the construction project for the new Blakely elementary school back three to four weeks, according to officials with the Bainbridge Island School District.

Mithun, the architects for the new school, said last July that the school would have a 13-month construction schedule, and expected that to conclude by March 2019.

A two-month commissioning contingency was included in the earlier project schedule, with the school being ready to open this September.

Ground was broken on the project last April for the new school, which was approved by Bainbridge voters via a bond measure in February 2016.

But after “Snowmagedden” struck in February, slippery conditions at the construction site delayed progress on the project.

District officials said crews worked overtime on the new elementary school on Saturdays in February to meet the schedule, and will continue working on Saturdays through March to put the school back on track.

School district officials said allowances as part of the original bid amount and contractor’s contingency will cover the overtime costs for most trades.

It’s not the first setback for the project’s schedule, though.

Last August, the International Union of Operating Engineers Local 302 went on strike, which kept heavy equipment operators, concrete pumpers, engineers and others off the job site. The strike ended in September, and crews worked on Saturdays to make up for the lost time, according to the school district.

Changes to the construction plan for Blakely have continued to be made in recent weeks.

The Bainbridge Island School Board will consider its sixth change order for the project, which includes toilet accessory revisions, powered roller shades in the library, changing the mechanical mezzanine in the gym from plywood to concrete, light fixture changes and other modifications.

The cost of the changes are $68,207.

Previous change orders have cut costs by $607,902 for the project.

If the school board agrees to the changes, the revised construction contract for the new Blakely will total $32,742,259.

State taxes on the project total $2.9 million, so the revised construction contract, with tax included, will total more than $35.6 million.

More in News

ABC bestows 2019 Environmental Award

Photo courtesy of Charles Schmid, Association of Bainbridge Communities Olaf Ribeiro presents… Continue reading

Councilman Peltier apologizes to Ethics Board for outburst at earlier meeting

Bainbridge Island Councilman Ron Peltier has sent a letter to the city’s… Continue reading

TRAVEL ADVISORY | Bainbridge ferries running late, one-hour wait at terminal

Washington State Ferries is advising travelers on the Bainbridge Island-Seattle route that… Continue reading

Trial again delayed for man accused of assaulting island teens

The trial of the Poulsbo man who was jailed last year after… Continue reading

Highway 305 trees get spotty

Travelers along Highway 305 on Bainbridge Island may have noticed spots of… Continue reading

Bullock studies abroad in France

Jem Bullock of Bainbridge Island participated in the fall 2018 Bates College… Continue reading

Two Bainbridge parks eyed as potential sites for more pickleball courts

Bainbridge parks officials will talk about the potential for new pickleball courts… Continue reading

Bainbridge blotter | Shattered, no suspects

Selected reports from the Bainbridge Island Police Department blotter. SATURDAY, FEB. 23… Continue reading

Daylight saving all the time proposed for state | 2019 Legislative Session

OLYMPIA — Washington residents could vote to make daylight saving time year-round… Continue reading

Most Read