More funding going toward city's Strawberry Plant Park project

The City Council has approved a second change order of $31,150 to cover additional costs necessary to complete the Strawberry Plant Park project.

The funds are being provided by the Elliot Bay Trustee Council, which approved an additional $181,539 last November to cover the unexpected costs associated with the project’s change order work.

The project was originally contracted for $848,544, but went over budget when the city ran into complications at the Eagle Harbor site.

The first change order was approved on Dec. 8, for $120,850. The second change order is for removal of the remaining on-site soils. The change increases the contract amount by 14.4 percent to $991,004.

Community Develop-ment Administrator Chris Wierzbicki said the city believes it will have a small amount of additional funding left over to begin the upland meadow work.

We encourage an open exchange of ideas on this story's topic, but we ask you to follow our guidelines for respecting community standards. Personal attacks, inappropriate language, and off-topic comments may be removed, and comment privileges revoked, per our Terms of Use. Please see our FAQ if you have questions or concerns about using Facebook to comment.
blog comments powered by Disqus

Read the latest Green Edition

Browse the print edition page by page, including stories and ads.

Sep 19 edition online now. Browse the archives.